Contract No. CM 04/2024 –

Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works – Environmental Team Services (2025 - 2027)

Monthly Environmental Monitoring and Audit Report for:

June 2025

Revision 2

 

 

 

Certified By:

 

 

 

______________

Ting Po Chung, Ivan

Environmental Team Leader

Report Date: 11 July 2025

 

 


 


Content:

 

1.         Introduction. 1

1.1       Project Background. 1

1.2       Environmental Monitoring & Audit Programme. 1

1.3       Monthly Environmental Monitoring & Audit Report 2

2.         Basic project Information and Environmental Status. 4

2.1       Basic Project Information. 4

2.2       Construction Programme. 4

2.3       Works undertaken during the Reporting Month. 5

2.4       Drawing Showing the Project Area, Environmental Sensitive Receivers and Monitoring Locations. 5

3.         Implementation Status. 6

3.1       Advice on the Implementation Status of Environmental Protection and Pollution Control/Mitigation Measures. 6

3.2       Environmental Mitigation Measures. 6

3.3       Environmental Monitoring Requirements and Contractual Requirements. 6

3.4       Site Inspection and Audit Reports. 7

4.         Noise Monitoring. 9

4.1       Monitoring Methodology. 9

4.2       Monitoring Stations. 10

4.3       Monitoring Date, Time, Frequency and Duration. 11

4.4       Noise Monitoring Results. 11

5.         Water Quality Monitoring. 12

5.1       Completion of Wqter Quality Monitoring. 12

6.         Ecology. 13

6.1       Monitoring Methodology. 13

6.2       Parameters Monitored. 13

6.3       Monitoring Location. 13

6.4       Monitoring Date, Time, Frequency and Duration. 13

6.5       Monitoring Results. 13

7.         Waste Management 14

8.         Complaints, Notification of Summons and Prosecution. 15

9.         Future Key Issues. 17

10.       Conclusion. 18

10.1     Noise Monitoring. 18

10.2     Water Quality Monitoring. 18

10.3     Ecological Impact Monitoring. 18

10.4     Review of the Reasons for and the Implications of Non-compliance. 18

10.5     Summary of Action Taken in the Event of and Follow-Up on Non-Compliance. 19

 

 

 

Tables:

 

Table 2.1:     Contact Details of Key Personnel

Table 3.1:     Summary of Submission Status under EP-538/2017

Table 3.2:     Summary of the Current Status on Licences and/or Permits on Environmental Protection Pertinent to The Project

Table 3.3:     Summary of Environmental Inspections

Table 4.1:     Noise Monitoring Equipment

Table 4.2:     Noise Monitoring Station

Table 7.1:     Summary of Quantities of Waste Material

Table 8.1:     Cumulative Statistics on Complaints

Table 8.2:     Summary of Complaints

Table 8.3:     Cumulative Statistics on Successful Prosecutions

Table 9.1:     Construction Activities and Recommended Mitigation Measures in Coming Reporting 3 Months

Table 10.1:        Summary of Ecological Impact Monitoring

 

Figures:

 

Figure 2.1        Master Layout Plan

Figure 2.2        Contract Layout Plan

Figure 2.3        Locations of Noise Monitoring Station

Figure 6.1        Mark up Figure 5.4i extracted from approved EIA Report (AEIAR-210/2017)

Figure 6.2        Location Plan for Temporary Holding Nursery

 

Appendices:

 

Appendix 4.1    Calibration Certificates for Noise Meter and Acoustic Calibrator

Appendix 4.2    Impact Monitoring Schedule for Construction Phase Noise Monitoring for the Reporting Month and Next Month

Appendix 4.3    Noise Monitoring Results and Graphical Presentations

Appendix 7.1    Monthly Summary Waste Flow Table

Appendix 9.1    3 Months Rolling Programme


Executive Summary

 

This Monthly Environmental Monitoring and Audit (“EM&A”) Report summarise project monitoring and auditing data, with full interpretation illustrating the acceptability or otherwise of any environmental impacts and identification or assessment of the implementation status of agreed mitigation measures, including monitoring results and findings of the EM&A Programme, along with findings recorded during the site Inspections and audits, reports of Complaints, Notifications of Summons and Successful Prosecutions, and other necessary observations obtained within this reporting month of June 2025.

In the reporting month, the principal work activities conducted are as follow:

Ÿ   Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road;

Ÿ   Trenchless drilling works (Chi Ma Wan Road);

Ÿ   Excavation and ELS work at POSPS;

Ÿ   Superstructure RC works at SSWSTW;

Ÿ   E&M Installation at POSPS

Noise Monitoring

Noise Monitoring has been conducted at 8 of the designated monitoring locations (N12a, N12b, N13, N14, N15b, N16a, N16b, and N17) where construction works has been conducted nearby during the reporting month.

During the reporting period, school examinations were held from 4 to 6, 9 and 16 to 17 June 2025. Accordingly, the noise limit for monitoring station N17-Bui O Public School was temporarily reduced to 65 dB(A) on these examination.

No action or limit level exceedance was recorded in construction noise level in this reporting period.

Water Quality Monitoring

Subsequent to the completion of marine work on 24 May 2025, water quality monitoring was considered completed by 30 May 2025. No water quality monitoring is conducted in this reporting month.

Should marine works resume, water quality monitoring will be conducted in accordance with the requirement stipulated in the EM&A Manual accordingly.

Ecological Impact Monitoring

Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding nursery have commenced.

As per latest version of PTP, 4 tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.

The weekly site audit was carried out by ET include checking whether good site practices are being properly implemented by the Contractor.

The extent of the work site boundaries was checked by the ET during the weekly site audit.

Complaints, Notification of Summons and Prosecution

No environmental complaint was recorded in the reporting month.

No notification of summons and successful prosecution regarding construction works were recorded in the reporting month.

Reporting Changes

There are no reporting changes in the reporting month.

Future Key Issues

The construction works scheduled to be conducted in the coming 3 reporting months are listed as follows:

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road;

·         Excavation and site formation at SSWSTW;

·         Trenchless drilling works (Chi Ma Wan Road);

·         Excavation and ELS work at POSPS;

·         Superstructure RC works at SSWSTW;

·         Retaining wall construction at SSWSTW;

·         E&M Installation at POSPS

Key construction activities for the next three months with the recommended mitigation measures to be implemented are presented as follows:

 

Key Construction Works

Recommended Mitigation Measures

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road

·         Excavation and site formation at SSWSTW

·         Trenchless drilling works (Chi Ma Wan Road)

·         Excavation and ELS work at POSPS

·         Superstructure RC works at SSWSTW

·         Retaining wall construction at SSWSTW

·         E&M Installation at POSPS

 

·         Prevention of site runoff during heavy rainstorms.

·         Implementation of noise pollution control in accordance with Construction Noise Mitigation Plan;

·         Dust control during dust generating works;

·         Adopt surface drainage and sediment control facilities for sewage installation in village and public roads;

·         Adopt temporary drainage and sediment control facilities on Site;

·         Vehicle wheel-washing and body washing facilities should be provided at the site entrance;

·         Regular water spraying on excavation works for dust control; and

·         Proper waste handling, recycling and storage.

 


1.                 Introduction

1.1              Project Background

1.1.1          The Environmental Protection Department (“EPD”) completed the Outlying Islands Sewerage Master Plan (“SMP”) Study in 1994 and drew up a SMP for Lantau Island and other outlying islands. The proposed sewerage works of the SMP were divided into 2 stages. The Stage 2 Works of the SMP were subsequently reviewed by EPD under the Outlying Islands Sewerage Master Plan Stage 2 Review (SMP Review Study) in 2001.

1.1.2          The proposed sewerage works for South Lantau were further reviewed in 2008 under the Review of Sewerage Scheme for South Lantau (Review Study). According to the Review Study, the proposed sewerage works for South Lantau would serve the unsewered areas of Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin.

1.1.3          The Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works, herein referred to as “the Project”, referred to the sewerage works for South Lantau that would serve the unsewered areas of Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin.

1.1.4          The Project mainly comprises of the following items:

a)  Construction of a secondary sewage treatment works (“STW”) at San Shek Wan in South Lantau;

b)  Construction of sewage pumping station (“SPS”) at Pui O, San Shek Wan, Cheung Sha, Cheung Fu Street, Shui Hau and Tong Fuk;

c)  Construction of about 1.4km of twin submarine outfalls with a diameter of 350mm for the disposal of treated effluent from the STW at San Shek Wan;

d)  Construction of about 10.1km of gravity sewers with diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma Wan Road and at Pui O; and

e)  Construction of about 3.1km of twin rising mains with a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.

1.2              Environmental Monitoring & Audit Programme

1.2.1          An Environmental Impact Assessment (“EIA”) was subsequently prepared to review the potential environmental impact that would be due to the Project during its construction works and operational works. The EIA Report was submitted and approved on 24 April 2017, and Environmental Permit (“EP”) No. EP-538/2017 was subsequently granted on 13 July 2017.

1.2.2          Environmental Monitoring & Audit (“EM&A”) Programme is therefore implemented in accordance with the EM&A Manual under the EIA Report.

1.2.3          Umwelt Consulting Limited (“UCL”) has been appointed to work as the Environmental Team (“ET”) under EP No. EP-538/2017 to implement the Environmental Monitoring and Audit (“EM&A”) programme as stipulated in the EM&A Manual of the approved EIA Report for the Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works (Register No.: AEIAR-210/2017).

1.3              Monthly Environmental Monitoring & Audit Report

1.3.1          This Monthly EM&A Report summarise project monitoring and auditing data, with full interpretation illustrating the acceptability or otherwise of any environmental impacts and identification or assessment of the implementation status of agreed mitigation measures, including monitoring results and findings of the EM&A Programme, along with findings recorded during the site Inspections and audits, reports of Complaints, Notifications of Summons and Successful Prosecutions, and other necessary observations obtained within this reporting month of June 2025.

1.3.2          The structure of this Report is detailed as follows:

a)  Section 1 Introduction –
Details the scope and structure of the report.

b)  Section 2 Basic project Information and Environmental Status –
Summarizes project organization and key personnel contact, construction programme and works undertaken for the month. Construction programme, works undertaken during the month with illustrations, drawing showing the project area, environmental sensitive receivers and monitoring locations.

c)  Section 3 Implementation Status –
Advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the EIA Report and summarised in the updated implementation schedule.

d)  Section 4 Noise Monitoring –
Summarizes the monitoring results obtained in the reporting period, including monitoring methodology, name of laboratory and equipment used and calibration details, parameters monitored, monitoring locations (and depth), monitoring date, frequency, and duration, for impact noise monitoring.

e)  Section 5 Water Quality Monitoring –
Summarizes the monitoring results obtained in the reporting period, including monitoring methodology, name of laboratory and equipment used and calibration details, parameters monitored, monitoring locations (and depth), monitoring date, frequency, and duration, for impact water quality monitoring.

f)   Section 6 Ecology –
Summarizes the audit findings during the reporting month on ecological aspects.

g)  Section 7 Waste Management –
Summarizes the status of waste management, including the amount and types of waste generated, and respective treatment approach.

h)  Section 8 Report on Complaints, Notification of Summons and Successful Prosecutions –
Summarizes:

Ø Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

Ø Record of notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

Ø Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and

Ø Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to non-compliance.

i)    Section 9 Future Key Issues –
An account of the future key issues as reviewed from the works programme and work method statements.

j)    Section 10 Conclusion –
Summarises the findings conclusion drawn from the environmental monitoring and audit programme in this reporting month.

2.                 Basic project Information and Environmental Status

2.1              Basic Project Information

2.1.1          Drainage Services Department (“DSD”) is the project proponent and the permit holder of the Project. For the construction phase of the Project, Contractor(s), ET and Independent Environmental Checker (“IEC”) are appointed to manage and control environmental issues. Key personnel and contact particulars are summarized in Table 2.1.

2.1.2          Upon conclusion of Contract No: SD 15/2022 Outlying Island Sewerage Stage 2 – South Lantau Sewage Works – Environmental Team Services (2023 – 2024), the subsequent contract, Contract No. CM 04/2024 Outlying Islands Sewerage Stage 2 – South Lantau Sewerage Works – Environmental Team Services (2025-2027), has been awarded to Umwelt Consulting Limited (“UCL”) starting 1 February 2025. As such the environmental team leader (“ETL”) appointed for the Project has been updated to Mr. Ting Po Chung, Ivan since 1 February 2025. His contact details has been updated in Table 2.1.

2.1.3          There are no other reporting changes in the reporting month.

Table 2.1:    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

Drainage Services Department

The Engineer for the Contract

Engineer

Mr. KK Chan

2594 7297

3104 6426

Binnies Hong Kong Limited

Engineer’s Representative

Resident Engineer

Mr. Kevin Chan

3529 3003

-

Kwan Lee – Chun Wo Joint Venture

Contractor

Sub Agent

Mr. Daniel Chu

6737 6701

2744 6937

Environmental Supervisor

Ms. Joey Pang

6978 2876

Environmental Supervisor

Mr. Philip Wong

6908 8920

SMEC Hong Kong

IEC

IEC

Ms. Kitty Lee

3995 8140

3422 3631

Umwelt Consulting Limited

ET

ET Leader

Mr. Ivan Ting

3756 9590

3582 3310

 

2.2              Construction Programme

2.2.1          The proposed sewerage works will collect the sewage generated from the unsewered areas of Shui Hau, Tong Fuk, Cheung Sha, San Shek Wan, Pui O and Ham Tin in South Lantau (i.e. within the Project Catchment Area) and convey it to a proposed sewage treatment works at San Shek Wan for treatment and disposal into outer bay of Pui O / Chi Ma Wan via a submarine outfall.

2.2.2          The Project was divided into 3 contracts. The current contract, Contract No. DC/2020/02 - Construction of San Shek Wan Sewage Treatment Works, Associated Submarine Outfall and Pui O Sewerage Works (“the Contract”) would have the following implementations. The works site of the Contract is also given in Figure 2.1.

2.2.3          The major components of the Contract under Environmental Permit (“EP”) (EP No. EP-538/2017) comprises:

a)  Construction of a secondary sewage treatment works (“STW”) at San Shek Wan in South Lantau;

b)  Construction of a sewage pumping station (“SPS”) at Pui O, San Shek Wan, Cheung Sha and Cheung Fu Street;

c)  Construction of about 1.4km of submarine outfall with a diameter of 350mm for the disposal of treated effluent from the STW at San Shek Wan;

d)  Construction of about 10.1km of gravity sewers with diameters ranging from 150mm to 375mm along South Lantau Road and Chi Ma Wan road and at Pui O; and

e)  Construction of about 3.1km twin rising mains with a diameter of 200mm to 250mm along South Lantau Road and Chi Ma Wan Road.

2.3              Works undertaken during the Reporting Month

2.3.1          In the reporting month, the principal work activities conducted are as follow:

a)  Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road

b)  Trenchless drilling works (Chi Ma Wan Road)

c)  Excavation and ELS work at POSPS;

d)  Superstructure RC works at SSWSTW;

e)  E&M Installation at POSPS;

2.3.2          The locations of the works are shown in Figure 2.2.

2.4              Drawing Showing the Project Area, Environmental Sensitive Receivers and Monitoring Locations

2.4.1          Noise and water monitoring location plans with sensitive receivers are shown in Figure 2.3 and Figure 2.4 respectively.

3.                 Implementation Status

3.1              Advice on the Implementation Status of Environmental Protection and Pollution Control/Mitigation Measures

3.1.1          Mitigation measures according to the environmental mitigation implementation schedule in Annex A of EM&A Manual were generally implemented by the Contractor. Hence, the EM&A programme was considered effective and shall be maintained.

3.2              Environmental Mitigation Measures

3.2.1          Environmental mitigation measures mentioned the EIA Report were weekly reviewed and recorded in Weekly Environmental Site Audit Checklist. Also, a summary of the current status on submissions and measures mentioned in the EP No. EP-538/2017 are shown in Table 3.1.

Table 3.1:    Summary of Submission Status under EP-538/2017

EP Condition

Submission and Revision No.

Date of Latest Submission

2.10

Waste Management Plan (Rev. 5) (electronic copy)

4 April 2022#

2.11

Preservation and/or Transplantation Plan for Plant Species of Conservation Importance (Rev. 23)

9 September 2022#

2.12

Compensatory Woodland Planting Plan (Rev. 23)

15 May 2023^

2.13

Silt Curtain Deployment Plan (Rev. 11)

1 June 2022#

2.14

Landscape Mitigation Plan

To be confirmed

2.15

Construction Noise Mitigation Plan (Rev. 20)

4 August 2022#

Note:

^    Submission was made to EPD

#    Approval from EPD was received

3.3              Environmental Monitoring Requirements and Contractual Requirements

3.3.1          A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.2.

Table 3.2:    Summary of the Current Status on Licences and/or Permits on Environmental Protection Pertinent to The Project

Permits and/or Licences

Permit. No. / Account No.

Issued Date

Valid Period & Expiry Date

Status

Notification of Works Under APCO

466408

14 Apr 2021

N/A

Valid

Wastewater Discharge Licence under Water Pollution Control Ordinance

SSWSTW: WT00039636-2021

30 Dec 2021

30 Dec 2021 to
31 Dec 2026

Valid

POPS: WT00039820-2021

31 Dec 2021

31 Dec 2021 to
31 Dec 2026

Valid

SSWSTW: Gravity Sewer & Raising Main: WT00042613-2022

09 Jan 2023

09 Jan 2023 to
31 Jan 2028

Valid

Billing account under Waste Disposal Ordinance

Account No.: 7040411

05 May 2021

N/A

Valid

Registration as a Chemical Waste Producer

0000-931-K3428-01

13 May 2021

N/A

Valid

Construction Noise Permit under Noise Control Ordinance for SSWSTW

GW-RS0084-25

28 Jan 2025

09 Feb 2025 to
08 Aug 2025

Valid

Construction Noise Permit under Noise Control Ordinance for POSPS

GW-RS0310-25

26 Mar 2025

28 Mar 2025 to

26 Sep 2025

Valid

Note: Only valid permits or permits under applications within the reporting month are included.

3.4              Site Inspection and Audit Reports

3.4.1          Within this reporting month, weekly environmental site inspections were conducted on 2, 9, 16, 23 and 30 June 2025. IEC attended the SSEMC meeting held on 16 June 2025. The ET and contractor participated in the holding nursery visit for transplanted trees on 30 June 2025.

3.4.2          No non-compliance was found during the site inspections while reminders on environmental measures were recommended. Reminders and/or Observations recorded during site inspections in this reporting month are listed in Table 3.3.

Table 3.3:    Summary of Environmental Inspections

Inspection Date

Reminder and Recommendations

Close-out Date / Status

2 June 2025

Pui O Sewage Pumping Station

No Reminder and/or Observation

San Shek Wan Sewage Treatment Works

Reminder 1

The contractor is reminded to instruct workers to sort waste properly.

Reminder 2

The contractor is reminded to remove standing water in the construction site.

 

Contractor has rectified the reminders on 16 June 2025

9 June 2025

Pui O Sewage Pumping Station

Reminder 1

The contractor is reminded to store the chemical container properly.

San Shek Wan Sewage Treatment Works

No reminder and/or observations

 

Contractor has rectified the reminders on 16 June 2025

16 June 2025

Pui O Sewage Pumping Station

Reminder 1

The contractor is reminded to properly store the chemicals on site.

San Shek Wan Sewage Treatment Works

Reminder 2:

The contractor is reminded to properly store the chemicals on site.

 

Contractor has rectified the reminders on 23 June 2025

23 June 2025

Pui O Sewage Pumping Station

No Reminder and/or Observation

San Shek Wan Sewage Treatment Works

Reminder 1:

The contractor is reminded to maintain the housekeeping.

 

Contractor has rectified the reminders on 30 June 2025

30 June 2025

Pui O Sewage Pumping Station

No Reminder and/or Observation

San Shek Wan Sewage Treatment Works

Reminder 1:

The contractor is reminded to maintain the housekeeping.

Kam Tin Nursery

Reminder 2:

The contractor is reminded to properly install the tree tag.

 

To be verified in next inspection

4.                 Noise Monitoring

4.1              Monitoring Methodology

Monitoring Procedure

4.1.1          The impact noise monitoring should be carried out at all the designated monitoring stations when there are project-related construction activities undertaken within a radius of 300m from the monitoring stations.

4.1.2          The monitoring station shall normally be at a point 1m from the exterior of the sensitive receiver’s building façade and be at a position 1.2m above the ground.

4.1.3          Façade measurements were made at the monitoring locations. For free-field measurement, a correction factor of +3dB(A) will be applied.

4.1.4          The battery condition was checked to ensure the correct functioning of the meter.

4.1.5          Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

a)  Frequency weighting: A,

b)  Time weighting: Fast,

c)  Measurement time set: continuous 5 mins

4.1.6          Prior and after to the noise measurement, the meter was checked using the acoustic calibrator for 94dB (A) at 1000 Hz. If the difference in the calibration level before and after measurement was more than ±1.0 dB (A), the measurement would be considered invalid and repeat of noise measurement would be required after recalibration or repair of the equipment.

4.1.7          Noise measurements will be made in accordance with standard acoustical principles and shall not be made in fog, rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

Equipment Used for Noise Monitoring

4.1.8          Noise monitoring was performed using sound level meter at the designated monitoring locations. The sound level meters shall comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator shall be deployed to check the sound level meters at a known sound pressure level. Brand and model of the equipment is given in Table 4.1.

Table 4.1:    Noise Monitoring Equipment

Equipment

Brand and Model

Serial Number

Valid Until

Integrated Sound Level Meter

Rion - NL-52

01198668

13 Jan 2026

Acoustic Calibrator

Rion - NC-75

34202223

13 Jan 2026

 

4.1.9          The calibration certificates of the noise monitoring equipment are attached in Appendix 4.1.

Calibration Details

4.1.10       The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

4.1.11       The sound level meter and calibrator were calibrated at yearly intervals.

Parameters Monitored

4.1.12       The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (“Leq”). Leq(30min) should be used as the monitoring parameter. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.13       For impact monitoring for construction of village sewers / rising main, noise monitoring should be undertaken on weekly basis. 1 set of Leq(30min) noise level as 6 consecutive Leq(5min) between 07:00-19:00 hours on normal weekdays has been taken.

4.2              Monitoring Stations

4.2.1          The noise monitoring stations for the Project are listed and shown in Table 4.2. Impact noise monitoring was conducted once per week at the noise monitoring stations with construction works being conducted nearby. Noise monitoring has been conducted at 8 noise monitoring stations N12a, N12b, N13, N14, N15b, N16a, N16b and N17 in the reporting month.

4.2.2          During the reporting period, school examinations were held from 4 to 6, 9 and 16 to 17 June 2025. Accordingly, the noise limit for monitoring station N17-Bui O Public School was temporarily reduced to 65 dB(A) on these examination. The standard noise limit of 70 dB(A) remained applicable for all other days outside this examination period.

Table 4.2:    Noise Monitoring Station

Monitoring Station ID +

Monitoring Location

Measurement Type

Level (in terms of no. of floor)

N01a

Shui Hau Village

Free-Field

G/F

N01c

Shui Hau Village

Free-Field

G/F

N03a

Tong Fuk Village

Free-Field

G/F

N05a

Residences at Cheung Fu Street

Free-Field

G/F

N07

Government Holiday Bungalows

Free-Field

G/F

N08

Cheung Sha Ha Tsuen

Free-Field

G/F

N10

Cheung Sha Sheung Tsuen

Façade

G/F

N11b

San Shek Wan – Ming Garden

Free-Field

G/F

N12a *

Lo Uk Tsuen

Free-Field

G/F

N12b *

Lo Uk Tsuen

Free-Field

G/F

N13 *

Pui O San Wai Tsuen

Free-Field

G/F

N14 *

South Lantau Community Centre

Free-Field

G/F

N15b *

Pui O Lo Wai Tsuen

Façade

G/F

N16a *

Residences at Ham Tin

Façade

G/F

N16b *

Residences at Ham Tin

Free-Field

G/F

N17 *

Bui O Public School

Façade

R/F

NOTE:

+     Fine adjustment of noise monitoring stations at all locations was proposed as per EP Condition 3.1.

*     Measurement was conducted at the station in the reporting month.

4.3              Monitoring Date, Time, Frequency and Duration

4.3.1          For daytime construction work on normal weekdays, monitoring of Leq(30min) should be carried out at each station at 0700-1900 hours on normal weekdays at a frequency of once a week. Impact monitoring schedule can be referred to Appendix 4.2.

4.4              Noise Monitoring Results

4.4.1          Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 4.3.

4.4.2          No action or limit level exceedance was recorded in construction noise level in this reporting period.

5.                 Water Quality Monitoring

5.1              Completion of Water Quality Monitoring

5.1.1          Subsequent to the completion of marine work on 24 May 2025, water quality monitoring was considered completed by 30 May 2025. No water quality monitoring is conducted in this reporting month.

5.1.2          Should marine works resume, water quality monitoring will be conducted in accordance with the requirement stipulated in the EM&A Manual accordingly.

6.                 Ecology

6.1              Monitoring Methodology

6.1.1          The weekly site audit to be carried out by the ET should include checking whether good site practices are being properly implemented by the Contractor

6.1.2          Impact monitoring of the transplanted Aquilaris sinensis at holding nursery and 1 retain tree of Aquilaris sinensis in SSWSTW Project Site, establishment and after-establishment caring measures of the compensatory mixed woodland to ensure the affected tree would not be affected by any unacceptable construction works. The trees would be treated with establishment works immediately after transplanting.

6.1.3          Site inspection at the nursery was conducted on 30 June 2025. One reminder was recorded.

6.2              Parameters Monitored

6.2.1          The extent of the work site boundaries should be checked by the ET during the weekly site audit. Any disturbance by the Contractor outside the works area especially any damage to the vegetation and surrounding habitats outside the Project area shall be reported to ER and IEC.

6.2.2          To identify any unacceptable construction works for the trees of Aquilaris sinensis during transplanting, establishment and after-establishment caring measures of the compensatory mixed woodland.

6.3              Monitoring Location

6.3.1          As per latest version of PTP, 4 tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW (Figure 6.1) which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery (Figure 6.2) at Kam Tin and eventually be transplanted to Pui O Pumping Station.

6.4              Monitoring Date, Time, Frequency and Duration

6.4.1          The recommended good site practices to be audited once every week as part of the site audit programme. The weekly site audit to be carried out by the ET includes checking whether good site practices are being properly implemented by the Contractor. Results are recorded in Weekly Environmental Site Audit Checklist.

6.4.2          Monitoring programme for post-transplantation was conducted on 30 June 2025 once per month.

6.5              Monitoring Results

6.5.1          The weekly site audit was carried out by ET include checking whether good site practices are being properly implemented by the Contractor.

6.5.2          The extent of the work site boundaries was checked by the ET during the weekly site audit.

6.5.3          Results and findings of site audit in this reporting month are listed in Table 3.3.

7.                 Waste Management

7.1.1          The quantities of waste for disposal in the Reporting Period are summarized in Table 7.1. The Monthly Summary Waste Flow Table is shown in Appendix 7.1.

Table 7.1:    Summary of Quantities of Waste Material

Waste Type

Quantity this month

Quantity (the end of last month)

Cumulative Quantity-to-Date

Hard Rock and Large Broken Concrete (Inert), in ‘000m3

0

0

0

Reused in this Contract (Inert), in ‘000m3

0

0

0

Reused in other Projects (Inert), in ‘000m3

0

0

0

Disposal as Public Fill (Inert), in ‘000m3

0.06

0.07

29.61789

Metals, in ‘000kg

26.0432

20.88

62.70697

Paper / Cardboard Packing, in ‘000kg

0.0943

0

1.12488

Plastics, in ‘000kg

0.0029

0

0.10306

Chemical Wastes, in ‘000kg

0

0

0

General Refuses, in ‘000kg

26.09

29.07

854.41

Marine Sediment (Type 1 – Open Sea Disposal), m3

0

0

1360.2

NOTE:

The inert waste disposal record up to 7 April 2025 was based on the onsite record from the contractor instead of the official record from the Mui Wo Public Fill Reception Facility due to the maintenance of the weighting bridge. The subsequent inert waste disposal record will adopt the recorded weight at the Mui Wo Public Fill Reception Facility.

8.                 Complaints, Notification of Summons and Prosecution

8.1.1          No environmental complaint was recorded in the reporting month.

8.1.2          No notification of summons and successful prosecution regarding construction works were recorded in the reporting month.

8.1.3          Cumulative statistic on complaints, summary of complaints and successful prosecutions are summarized in Table 8.1, Table 8.2 and Table 8.3 respectively.

Table 8.1:    Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Project commencement to the end of last reporting month

3

This Reporting Month (June 2025)

0

Total:

3

 

Table 8.2:    Summary of Complaints

Date of Notification from EPD

Date of Complaint

Description of Complaint

Validity of Complaint

Close-Out Date / Status

26 May 2022

22 May 2022

A complaint is regarding to noise nuisance from marine site of San Shek Wan, Lantau Island.

Based on the investigation, the works activities of marine works did not result in any noise nuisance to Noise Sensitive Receivers (NSRs), noise nuisance from the Project is unlikely to be valid.

The interim report was submitted to EPD in June 2022. EPD replied no further comments on the final investigation report on 13 July 2022.

23 Dec 2022

21 Dec 2022

A complaint is regarding to the water quality for Pui O Beach, Lantau Island.

Based on the investigation, the works activities at POPS did not result in any water quality impacts to the Pui O Beach.

The interim report was submitted to EPD on 4 Jan 2023.

16 Aug 2024

15 Aug 2024

A complaint is regarding to the damaged silt curtain and potential water quality impact.

Based on the investigation, no marine works since Dec 2023 till present, the land based works activities at POPS did not result in any water quality impacts to the Pui O Wan

The interim report was submitted to EPD on 31 Aug 2024.

 

Table 8.3:    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Other

-

0

0

Total

-

0

0

 

9.                 Future Key Issues

9.1.1          In coming reporting 3 months, the scheduled construction activities are listed as follows:

Ø Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road

Ø Excavation and site formation at SSWSTW

Ø Trenchless drilling works (Chi Ma Wan Road)

Ø Excavation and ELS work at POSPS

Ø Superstructure RC works at SSWSTW

Ø Retaining wall construction at SSWSTW

Ø E&M Installation at POSPS

9.1.2          The scheduled construction activities and the recommended mitigation measures for the coming 3 months are listed in Table 9.1. The major construction activities for the next 3 months are summarized in 3 Months Rolling Programme – July 2025 to September 2025 in Appendix 9.1

Table 9.1:    Construction Activities and Recommended Mitigation Measures in Coming Reporting 3 Months

Key Construction Works

Recommended Mitigation Measures

·         Excavation, sewer laying, construction of manhole at Pui O Lo Uk Tsuen, South Lantau Road, Chi Ma Wan Road

·         Excavation and site formation at SSWSTW

·         Trenchless drilling works (Chi Ma Wan Road)

·         Excavation and ELS work at POSPS

·         Superstructure RC works at SSWSTW

·         Retaining wall construction at SSWSTW

·         E&M Installation at POSPS

 

·         Prevention of site runoff during heavy rainstorms.

·         Implementation of noise pollution control in accordance with Construction Noise Mitigation Plan;

·         Dust control during dust generating works;

·         Adopt surface drainage and sediment control facilities for sewage installation in village and public roads;

·         Adopt temporary drainage and sediment control facilities on Site;

·         Vehicle wheel-washing and body washing facilities should be provided at the site entrance;

·         Regular water spraying on excavation works for dust control; and

·         Proper waste handling, recycling and storage.

 

 

10.              Conclusion

10.1           Noise Monitoring

10.1.1       Noise Monitoring has been conducted at 8 of the designated monitoring locations where construction works has been conducted nearby during the reporting month.

10.1.2       During the reporting period, school examinations were held from 4 to 6, 9 and 16 to 17 June 2025. Accordingly, the noise limit for monitoring station N17-Bui O Public School was temporarily reduced to 65 dB(A) on these examination days. The standard noise limit of 70 dB(A) remained applicable for all other days outside this examination period.

10.1.3       No action or limit level exceedance was recorded in construction noise level in this reporting period.

10.2           Water Quality Monitoring

10.2.1       Subsequent to the completion of marine work on 24 May 2025, water quality monitoring was considered completed by 30 May 2025. No water quality monitoring is conducted in this reporting month.

10.3           Ecological Impact Monitoring

10.3.1       Transplanting of the trees of Aquilaris sinensis was completed on 26 April 2022. Maintenance works for trees in holding nursery have commenced.

10.3.2       As per latest version of PTP, 4 tree found (1 no. of Aquilaria sinensis and 3 nos. of Gmelina chinensis) within the site of SSWSTW which are considered to be the plant species with conservative importance for temporarily transplanted to the nursery at Kam Tin and eventually be transplanted to Pui O Pumping Station.

10.3.3       The weekly site audit was carried out by ET include checking whether good site practices are being properly implemented by the Contractor.

10.3.4       The extent of the work site boundaries was checked by the ET during the weekly site audit.

10.3.5       Within this reporting period, holding nursery visit for transplanted trees on 30 June 2025.

10.3.6       No non-compliance was found during the site inspection while reminders on environmental measures were recommended. Results and findings of these inspections in this reporting period are listed below in Table 10.1

Table 10.1: Summary of Ecological Impact Monitoring

Inspection Date

Reminder and Recommendations

Close-out Date / Status

30 June 2025

The contractor is reminded to properly install the tree tag.

 

In Section 3.4.2: to be verified in next inspection

10.4           Review of the Reasons for and the Implications of Non-compliance

10.4.1       No environmental non-compliance was recorded in the reporting month.

10.5           Summary of Action Taken in the Event of and Follow-Up on Non-Compliance

10.5.1       There was no particular action taken since no non-compliance was recorded in the reporting period.

10.5.2       The performance of the environmental management system of the reporting period was generally satisfied. Mitigation measures according to the environmental mitigation implementation schedule and the EIA were generally implemented by the Contractor. Hence, the EM&A programme was considered effective and shall be maintained.